Wallonia orders halt to Google data centre construction

A verbal stop order follows a dispute over changes to the plans for the Aiseau-Presles site. The original permit remains valid, according to the regional minister's office.

Published:

Based on: La Libre Belgique, itdaily.fr, itdaily.be

AI-assisted · source-checked3 sources

File photo of Google
Illustration: Google (file photo) · Photo: Asoundd · Source: Wikimedia Commons · CC BY-SA 4.0

Saved articles and followed stories stay in this browser. No account sync or notifications.

In 30 seconds

Wallonia has ordered work halted at Google’s data-centre site after rejecting changes to its plans, while the original permit remains valid and the dispute over water use and construction continues.

  • The regional stop order was given verbally on 26 November 2026, according to La Libre Belgique, which cited regional official Raphaël Stokys.
  • Google’s original permit, issued in 2024, covered three buildings. The regional minister’s office says that permit remains valid, but does not authorise construction under the revised plans.
  • The revised proposal combined two buildings and changed the planned cooling system from air to water drawn from the Sambre. Minister François Desquesnes opposed the change, citing the data centre’s water needs.
  • The Council of State is due to examine Google’s appeal on 7 January. Regional officials are checking whether the ongoing works comply with the rules; Greenpeace’s urgent procedure is also under way.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

What it means

What’s at stake

The immediate issue is whether construction can proceed under the initial permit or whether work linked to the revised plans must stop. The dispute also concerns a design that would use water from the Sambre for cooling, and Greenpeace’s separate claims about water use at Google’s Saint-Ghislain facility. The Council of State’s review, regional compliance checks and Greenpeace’s urgent procedure are all still pending, leaving the site’s permitted construction path unresolved in the reports.

Sources: itdaily.fr · itdaily.be · La Libre Belgique

What happens next

The Council of State is scheduled to consider Google’s appeal on 7 January. Meanwhile, regional officials are checking whether the works comply with the rules. If they find infringements, ITdaily reports, a formal report will be sent to the public prosecutor. The supplied reports do not say what the Council of State will decide or when the checks will conclude.

Sources: itdaily.fr · itdaily.be

Context

Background

Google received a permit in 2024 for three data-centre buildings at the Ecopôle site. In 2025, it sought to change the layout by combining two of them into one substantially larger building and replacing planned air cooling with water cooling using water from the Sambre. The regional administration approved the modification in April, according to ITdaily, and a citizen appeal followed the next month. In August, Walloon minister François Desquesnes opposed the change, citing the centre’s water needs. Google then appealed to the Council of State. The current dispute turns on the difference between the initial permit, which the minister’s office says remains valid, and the modified plans, which it says cannot be used for construction.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

The wider picture

The dispute is not simply over whether the site has a permit: the regional minister’s office distinguishes the 2024 permit from the later, modified plans. Water is central to that distinction because the revised proposal would use water from the Sambre for cooling. Greenpeace has also linked the project to Google’s water use at Saint-Ghislain, saying a comparable facility there pumps a billion litres of water a year for cooling and returns only a quarter. That figure and comparison are Greenpeace’s claims as reported by ITdaily, not an independently established finding in the supplied material.

Sources: itdaily.fr · itdaily.be

Why now

Greenpeace announced an urgent procedure on 25 November 2026 seeking an immediate halt to the works, saying satellite images showed that construction had continued. The regional stop order followed on 26 November, after officials inspected the site.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

How we got here

  1. Google received an initial permit for three data-centre buildings.

  2. Google sought to combine two proposed buildings into a larger one and replace planned air cooling with water cooling using water from the Sambre.

  3. Minister François Desquesnes opposed the modified plans, citing the data centre’s water needs.

  4. Greenpeace announced an urgent procedure seeking an immediate stop to the construction work.

  5. Wallonia issued a verbal order to stop work at the site.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

Reporting

Work ordered to stop

Wallonia ordered work to stop at the Google data centre construction site in Aiseau-Presles on 26 November 2026, La Libre Belgique reported. The newspaper cited regional official Raphaël Stokys, who said the order was given verbally. He told the paper that around 300 workers were on the site when officials made their inspection, despite a refusal of permission for part of the revised project in August.

Reporting

A project across municipalities

ITdaily reported that Google is building through its European subsidiary Crystal Computing at Ecopôle, a business park extending across Farciennes, Aiseau-Presles and Sambreville. The company's plot covers 53 hectares, according to the publication. La Libre Belgique reported that the initial building permit, issued in 2024, covered 3 buildings. The later application changed the arrangement of the buildings, creating a dispute over what could be constructed.

Key line

Regional official Raphaël Stokys said about 300 workers were on the site during the inspection.

— La Libre Belgique

Reporting

The disputed changes

According to ITdaily, Google applied in 2025 to combine 2 of the proposed buildings and replace the planned air-cooling system with water cooling using the Sambre. The regional administration approved the change in April, the publication reported, before minister François Desquesnes opposed it in August, citing the centre's water needs. Google subsequently took the decision to the Council of State, ITdaily said.

Reporting

Water and planning

The distinction between the original and revised plans matters for the future of the site. ITdaily reported that the office of François Desquesnes considers the original permit still valid, while construction under the changed plans is not permitted. Greenpeace has also raised concerns about water use, comparing the project with a Google facility in Saint-Ghislain. The organisation says only part of the water pumped there for cooling is returned, according to ITdaily.

Reporting

Appeal and inspections

Greenpeace announced an urgent procedure on 25 November seeking to stop the works, ITdaily reported, citing the organisation's assessment of satellite images. The Council of State is due to examine Google's appeal on 7 January, while regional officials check the works, the publication said. In a response reported by La Libre Belgique, a Google spokesperson said the company wanted an open and collaborative dialogue with the regional government and experts about its Walloon investments.

Understanding the story

What the main actors are doing

Reported positions, summarised — not direct quotations

Greenpeace

Greenpeace announced an urgent procedure to stop the works, saying satellite images showed that construction had continued. It has also raised concerns about water use and compared the project with Google’s facility in Saint-Ghislain.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

Google

Google sought approval for revised plans and has appealed the minister’s decision to the Council of State. A spokesperson said the company was committed to open and collaborative dialogue with the regional government and experts about its investments in Wallonia.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

François Desquesnes

The Walloon minister opposed the revised plans in August, citing the data centre’s water needs. Google subsequently appealed his decision to the Council of State.

Sources: itdaily.fr · itdaily.be

Voices & reactions

Google

A Google spokesperson said the company was committed to open and collaborative dialogue with the regional government and experts about its investments in Wallonia.

Sources: La Libre Belgique

People, places and institutions

  • GoogleThe company behind the data-centre project and the appeal against the minister’s decision.
  • GreenpeaceThe organisation that announced an urgent procedure to seek a halt to the construction work and raised concerns about water use.
  • François DesquesnesThe Walloon minister who opposed the modified plans, citing the centre’s water needs.
  • EcopôleThe business park where Google is building the data-centre complex, spanning Farciennes, Aiseau-Presles and Sambreville.

Sources: La Libre Belgique · itdaily.fr · itdaily.be

Some background items were left out because automated checks could not verify them against the sources.

People, places and organisations in this story

File pictures of subjects named in the article, not pictures of the events reported.

Logo of Greenpeace
Logo: Greenpeace · Photo: Stichting Greenpeace Council · Source: Wikimedia Commons · Public domain

Corrections policyReport an error

Sources and factual attribution (3)
  1. La Wallonie impose l'arrêt du chantier du data center de Google à Aiseau-Presles — La Libre Belgique

    Dated report by La Libre Belgique used for the facts attributed to it.

    Source publication date: . Consulted: .

  2. La Région wallonne suspend la construction du centre de données de Google à Farciennes - ITdaily — itdaily.fr

    Dated report by itdaily.fr used for the facts attributed to it.

    Source publication date: . Consulted: .

  3. Waals Gewest legt bouw van Google-datacenter in Farciennes stil - ITdaily — itdaily.be

    Dated report by itdaily.be used for the facts attributed to it.

    Source publication date: . Consulted: .

Supports

How this article was prepared

Revisions and corrections

No corrections recorded.

  1. First version · 1 —

    First publication.

How this article was prepared

Published after automated checks (sources, figures, language, independent AI fact-check):

Preparation note recorded before publication

Written by Belgium Pulse’s AI newsroom from the captured public sources listed below and published after automated source, figure, language and fact checks. No original on-site reporting; no human pre-publication review.

Belgium Pulse AI newsroom · Prepared:

Current revision: 1

↑ Back to article

Explore in Atlas

Places, people and organisations in this story, in Ordinis Atlas.