Why has Belgium’s Court of Audit sharply criticised the financing of the Liège tram?
Belgium’s Court of Audit has sharply criticised the financial management of the Liège tram project, whose dedicated Walloon budget allocation reaches €40.015 million in 2026, up from the €30.7 million in operator payments budgeted for 2025.
In 30 seconds
- Wallonia allocated €40.015 million in 2026 to the tram fee, mediation balance, out-of-configuration works and some priority-bus expenditure.
- OTW had budgeted €30.7 million for payments to Tram’Ardent in 2025, due to begin once the tram entered service.
- The 2019 financing announcement valued construction and maintenance under the PPP at about €430 million through January 2050.
- The European Investment Bank provided 50% of the long-term lending announced at financial close.
Key fact
€40.015 million Wallonia allocated in 2026 to the tram fee, mediation balance, out-of-configuration works and some priority-bus expenditure.
Belgium’s Court of Audit sharply criticised the financing of the Liège tram project in a report publicised on 3 September 2026, renewing scrutiny of a public-private partnership for which Wallonia has allocated €40.015 million this year. That is roughly €9.3 million more than the €30.7 million that the Opérateur de Transport de Wallonie, or OTW, had budgeted for payments to the private consortium Tram’Ardent in 2025, although the two figures do not cover exactly the same basket of costs. According to reporting by La Dernière Heure and 7sur7, the audit is particularly severe about the way the project’s financing was organised and monitored.
The criticism matters because the tram is no longer merely a construction project. It became an operating public service in April 2025, meaning the financial model has moved into its long repayment and maintenance phase. Wallonia’s 2026 budget documents say the €40.015 million credit principally covers the fee due under the public-private partnership, the balance of a mediation settlement and works outside the original project configuration. A smaller part supports studies and works for priority bus routes chosen after the regional government abandoned the tram’s short extensions in 2024.
That mixture of annual availability payments, settlement costs and supplementary works makes the true bill harder for a non-specialist reader to follow. It also explains the Court of Audit’s importance: the institution examines whether public money is authorised, recorded and reported in a way that allows the Walloon Parliament to exercise meaningful control. The published news accounts characterise its conclusions as damning, but the material available at publication does not establish one definitive, all-inclusive lifetime cost calculated on a single basis. Construction expenditure, financing charges, maintenance, compensation and associated public works should therefore not be casually added together.
At the centre of the arrangement is Tram’Ardent, the private project company responsible under a design-build-finance-maintain contract for delivering and maintaining the line. The consortium brought together industrial and financial partners including Colas and Spanish rolling-stock manufacturer CAF. The European Investment Bank supplied half of the long-term lending announced at financial close, alongside lenders including Belfius, BBVA and Natixis. OTW, the public operator trading under the TEC brand, runs the service and pays the contractual fee, with Wallonia ultimately backing the obligation.
When the financing was announced in January 2019, TEC described construction and maintenance under the contract as costing about €430 million through January 2050. The model was intended to transfer construction and availability risks to the private partner: payments would start only when the infrastructure entered service, and deductions could apply if the system was unavailable or defective. In theory, that aligns the contractor’s incentives with timely delivery and reliable performance. In practice, the line arrived years later than initially envisaged, following redesign, the pandemic, disputes and mediation between the public and private parties.
The broader economic lesson is not that every public-private partnership is inherently poor value. It is that deferred payment can obscure the trade-off between short-term budget relief and long-term rigidity. A PPP can bring private financing and specialised project management, but the public authority still needs the technical and legal capacity to challenge cost changes, document risk transfers and compare the final arrangement with conventional public procurement. If those controls are weak, an annual fee can resemble a manageable operating expense while binding future governments for decades.
There is also a European accounting history behind the dispute. Eurostat twice challenged an earlier financing structure in 2015 because the allocation of risk did not justify keeping the investment outside the public accounts. The project was subsequently reworked. The European Investment Bank then supported the revised financing under the Juncker Plan, while a Walloon decree provided a regional guarantee for the amounts owed by OTW. Those interventions did not remove the underlying public exposure; they determined how the risks and payments were structured and recorded.
For Liège households and businesses, the immediate issue is not a new tram surcharge. The cost is borne through Wallonia’s transport budget, where it competes with bus services, fleet renewal, school transport and other infrastructure. A fixed contractual payment must be honoured before policymakers decide how much discretionary money remains. If financing or supplementary works cost more than expected, the practical consequences can appear elsewhere: postponed investment, pressure on the wider TEC offer or additional demands on regional revenue. Conversely, a dependable tram can shorten journeys, improve access to the city centre and support shops and employers after years of disruptive construction.
The political perspectives therefore diverge without being mutually exclusive. The Court of Audit and parliamentarians concerned with budget control can reasonably demand a complete, comparable account of commitments and stronger documentation of decisions. OTW and the Walloon government can point to the fact that a complex infrastructure asset is now carrying passengers and that a DBFM contract includes decades of maintenance rather than construction alone. Businesses and passengers are likely to judge the project less by accounting architecture than by punctuality, connections and whether the reorganised bus network works.
The next test is the official response. Walloon ministers and OTW will need to explain which recommendations they accept, whether reporting to Parliament will change and how annual tram obligations fit into the operator’s wider funding settlement. Passenger numbers, service reliability, contractual deductions and the cost of remaining works will show whether the operating benefits justify the locked-in expenditure. Until the authorities publish a reconciled figure separating the base contract, finance, maintenance, settlements and ancillary works, claims about one definitive total should be treated cautiously.
What to do
Passengers face no confirmed new charge because of the report. The practical risk is indirect: a rigid or rising tram bill could constrain money available for bus frequency, vehicle replacement and other regional transport investments.
Impact
Regional — The issue is directly Walloon: regional taxpayers finance the obligations, OTW operates the service, and Liège residents and businesses depend on the tram and its connecting bus network.
EvidenceWell established · 1 primary source + 4 official documents + 2 independent reporting sources · Background sources: 1Explore evidence →Hide evidence ↑
- Published:
- 3 Sept 2026, 02:00
- Retrieved by ODIN:
- 3 Sept 2026
- Published:
- 3 Sept 2026, 02:00
- Retrieved by ODIN:
- 3 Sept 2026
- Publication date unavailable
- Retrieved by ODIN:
- 3 Sept 2026
- Publication date unavailable
- Retrieved by ODIN:
- 3 Sept 2026
- Published:
- 28 Apr 2025, 02:00
- Retrieved by ODIN:
- 3 Sept 2026
- Published:
- 31 Jan 2019, 01:00
- Retrieved by ODIN:
- 3 Sept 2026
- Published:
- 12 Feb 2026, 01:00
- Retrieved by ODIN:
- 3 Sept 2026
- Published:
- 13 Dec 2023, 01:00
- Retrieved by ODIN:
- 3 Sept 2026
Continue reading
This story was assembled from verified evidence, with its sources and reasoning recorded as it was written.

