Can Flanders still meet its 2030 onshore wind target after adding only two turbines?

Flanders added only two onshore wind turbines, delivering 6.75 megawatts, between 1 January and 1 June 2026, deepening doubts about whether the region can reach its 2,800 MW target by 2030.

Belgium Impulse Editorial·27 August 2026·5 min read·
Well established· 2 primary sources + 2 official documents + 1 independent reporting source
TopicsFlanders onshore wind targetFlemish wind energy2030 renewable energy targetVEKAJo BrounsMelissa DepraetereNadia NajiODE Vlaanderen

In 30 seconds

  • Only two turbines, in Arendonk and Tessenderlo-Ham, were added between 1 January and 1 June 2026.
  • The two machines provide a combined 6.75 MW of capacity.
  • Flanders aims for approximately 2,800 MW of onshore wind by 2030.
  • Installed capacity at the end of 2025 was reported at roughly 1,929 to 1,940 MW.

Flanders added only two onshore wind turbines between 1 January and 1 June 2026, in Arendonk and Tessenderlo-Ham, according to figures Flemish Environment Minister

Person

Jo Brouns

Flemish minister responsible for environment and permits who supplied the deployment figures.

Why it matters

Flemish minister responsible for environment and permits who supplied the deployment figures.

provided to parliament. Together they supply 6.75 megawatts of capacity. The exceptionally weak first five months leave the region far behind the pace required to meet its 2030 wind target and sharpen a Belgian challenge already identified by the European Commission: renewable energy is not being deployed quickly enough.

For households and businesses in Flanders, the issue reaches beyond the appearance of the landscape. More domestically generated electricity can reduce exposure to volatile imported gas, while additional renewable capacity will be needed as transport, heating and industry electrify. Yet turbines take years to move from an application to operation, meaning decisions made now shape the electricity system near the end of the decade.

The slowdown has become increasingly visible. De Standaard-group newspaper Het Nieuwsblad reported that annual additions fell from 49 turbines in 2022 to 17 in 2023, 20 in 2024 and around a dozen in 2025. Industry federation ODE Vlaanderen separately recorded 13 new turbines and roughly 50 MW of additional capacity in 2025, bringing the operational fleet to 722 turbines and 1,929 MW. Small differences between reported year-end totals can reflect updates and registration timing.

Those timing effects matter. The Flemish Energy and Climate Agency, VEKA, warns that recently commissioned turbines may enter network operators’ data several months late and that the newest quarter is therefore normally understated. Brouns, a CD&V minister, consequently called the two-turbine figure highly provisional. His office said the current Flemish government had approved 75 turbines, including 44 since revised siting rules took effect, and argued that construction totals can swing sharply when an entire wind farm happens to enter service.

Groen parliamentarian Nadia Naji reads the same evidence differently. She argues that 2026 risks becoming the weakest year on record and links the deterioration partly to rules introduced in April 2025 requiring a turbine in relation to residential areas to stand at least three times its tip height from the nearest home. For a 200-metre turbine, that example implies 600 metres. The rules were accompanied by greater flexibility for projects on industrial land, while Brouns disputes that they have reduced permitting.

Ghent University energy specialist Joannes Laveyne offered a third explanation to Het Nieuwsblad. He pointed to investment uncertainty after an earlier withdrawal of support, rather than treating the new distance rule as the sole cause. Flemish Energy and Climate Minister Melissa Depraetere subsequently restored access to green-power certificates for qualifying projects. Laveyne expects that intervention to help, but says the strongest sites are increasingly occupied and that the large expansion rates of a decade ago are unlikely to return.

That shifts attention towards repowering: replacing older machines with fewer, more powerful turbines. Motorway corridors and industrial zones may offer further space, but local opposition, environmental assessments and litigation can still lengthen the journey from permit to construction. ODE Vlaanderen says stable investment conditions and more legally robust, faster permit procedures are essential. Residents near proposed sites, however, retain legitimate interests concerning noise, shadow flicker, landscape and nature, which helps explain why faster approval cannot simply mean removing scrutiny.

The arithmetic is unforgiving. Flanders is aiming for about 2,800 MW of onshore wind by 2030. The end-2025 total was reported at roughly 1,929 to 1,940 MW, leaving around 860 MW to add. Naji calculates that approximately 175 MW must now be installed each year, against an average annual gain of about 59 MW over the previous three years. Brouns and Depraetere maintain that the target remains achievable, but neither has yet demonstrated through completed projects how the present gap will close.

The European backdrop increases the pressure without changing the essentially Flemish nature of the story. In January 2026, the European Commission said Belgium’s updated National Energy and Climate Plan had become more ambitious but still lacked sufficient ambition and deployment trajectories for renewable energy. EU renewable targets are collective, while the practical choices over Flemish onshore siting, permits and support largely sit with the regional government.

The next meaningful test will therefore be the full-year 2026 total, after delayed registrations are incorporated. Attention will also turn to whether the restored certificates unlock final investment decisions, how many of the 75 permitted turbines reach construction, and whether repowering can supply capacity faster than entirely new sites. Two turbines do not by themselves settle the year, but they make the distance between political approval and steel in the ground impossible to ignore.

Who’s affectedFlemish electricity consumersresidents near proposed wind sitesFlemish municipalitiesindustrial electricity usersonshore wind developersrenewable-energy investorsBelgian climate policymakers
Context & what happens next

What to do

For residents, businesses and energy professionals, the immediate point is that the 2030 target is not yet matched by the documented construction pace. People living near prospective wind sites should watch municipal and Flemish permit notices for consultations concerning noise, landscape and nature. Companies planning electrification should not assume that the remaining roughly 860 MW gap will be closed without faster approvals and construction. Policymakers and sector participants should watch subsequent VEKA updates because registration delays may revise the early-2026 figure. The decisive date remains 2030, with permitting and investment decisions before then determining whether the target is reachable.

Impact

Regional — The immediate impact falls on Flanders, where regional authorities control important aspects of renewable support, spatial planning and environmental permitting. Communities near possible sites face local noise, landscape and nature questions, while industrial zones and motorway corridors may carry more of the future build-out.

Evidence
Well established · 2 primary sources + 2 official documents + 1 independent reporting source
Explore evidence
Het Nieuwsblad
Published:
27 Aug 2026, 02:00
Retrieved by ODIN:
26 Aug 2026
Read original
Flemish Energy and Climate Agency
Publication date unavailable
Retrieved by ODIN:
26 Aug 2026
Read original
ODE Vlaanderen
Published:
13 Jan 2026, 01:00
Retrieved by ODIN:
26 Aug 2026
Read original
European Commission Directorate-General for Energy
Published:
26 Jan 2026, 01:00
Retrieved by ODIN:
26 Aug 2026
Read original

Voices & reactions

What the main actors are doing

Reported positions, summarised — not direct quotations

Nadia Naji and Groen

Naji says the addition of barely two turbines shows that Flanders is moving away from, rather than towards, its 2030 target. She associates the deeper slowdown with the Flemish government’s revised distance requirements and calculates that the recent average of about 59 MW a year would postpone the target until around 2040.

Jo Brouns and the Flemish government

Brouns calls the two-turbine tally a very provisional snapshot because commissioning is uneven and recent registrations are incomplete. His office points to 75 approved turbines during the current government’s term, including 44 after the revised rules, and says permit numbers have not fallen.

Joannes Laveyne and the investment explanation

Laveyne identifies earlier policy uncertainty over financial support as an important cause of weak construction and expects restored green-power certificates to help. Even so, he believes scarce sites mean that repowering existing locations, rather than another large wave of entirely new sites, will drive future gains.

ODE Vlaanderen and wind developers

The sector argues that legally robust permits, faster procedures and predictable investment support are necessary to reach 2,800 MW. This differs from a simple targets-first framing: developers stress the bankability and buildability of projects, while nearby residents retain concerns about noise, landscape, shadow and nature.

The story, connected

Explore the people, places and ideas in this story

Go beyond the headline. Open a card for sourced context, maps, official links and the other subjects connected to this report.

People

Jo Brouns

Flemish minister responsible for environment and permits who supplied the deployment figures.

In this story

Flemish minister responsible for environment and permits who supplied the deployment figures.

Organisations

European Union

Supranational framework within which Belgium pursues climate and renewable-energy objectives.

In this story

Supranational framework within which Belgium pursues climate and renewable-energy objectives.

Background

The European Union (EU) is a political and economic union of 27 member states that are located primarily in Europe. A supranational union with a total area of 4,233,255 km2 (1,634,469 sq mi) and an estimated population of just under 452 million as of 2026, its member states generated a nominal gross domestic product (GDP) of around €18.802 trillion in 2025, accounting for approximately one sixth of global economic output.

Concepts

Flemish 2030 onshore wind target

Regional objective to reach approximately 2,800 MW of installed onshore wind capacity by 2030.

In this story

Regional objective to reach approximately 2,800 MW of installed onshore wind capacity by 2030.