Bad weather delays opening of new Firtelbrug cycle bridge in Zulte until spring
De Vlaamse Waterweg could not lay the anti-slip coating on the bridge deck in damp, cold conditions, so cyclists and pedestrians will have to wait several more months.
Published: · Content updated:
Based on: VRT NWS

Saved articles and followed stories stay in this browser. No account sync or notifications.
Key facts
- Cyclists and pedestrians will only be able to use the new Firtelbrug in Zulte from the spring. (VRT NWS)
- Because of damp air and temperatures that were too low, De Vlaamse Waterweg could not yet apply the anti-slip coating to the bridge deck. (VRT NWS)
- Without the anti-slip coating there is a risk of falls, and users could also damage the bridge by walking on it. (VRT NWS)
- The bridge links the centre of Zulte via the Limnanderdreef to the towpath on the other bank of the Leie, giving cyclists direct access to the F371 cycle highway. (VRT NWS)
In 30 seconds
The new Firtelbrug for cyclists and pedestrians in Zulte will only open in the spring because bad weather prevented De Vlaamse Waterweg from laying the anti-slip coating, without which users risk falling.
- According to VRT NWS, cyclists and pedestrians will only be able to use the new Firtelbrug in Zulte from the spring.
- Damp air and temperatures that were too low meant the anti-slip layer on the bridge deck could not yet be applied.
- Without the coating there is a risk of falls, and users could also damage the bridge by walking or riding on it.
- The bridge links the centre of Zulte via the Limnanderdreef to the towpath across the Leie, giving cyclists direct access to the F371 cycle highway.
Sources: VRT NWS
What it means
What happens next
The bridge is now expected to open to cyclists and pedestrians in the spring, once the anti-slip layer can be applied. The report gives no precise opening date and does not say how long the coating work will take or whether the delay affects the project's cost.
Sources: VRT NWS
Context
The wider picture
Zulte is a municipality in the province of East Flanders, made up of Machelen, Olsene and Zulte proper. It lies on the Leie, a river rising in France that flows into the Scheldt in Ghent. The new bridge is meant to connect the town centre on one bank with the towpath and the F371 cycle highway on the other.
Sources: VRT NWS · Wikipedia: Zulte (Background reference) · Wikipedia: Lys (river) (Background reference)
Why now
The Firtelbrug was normally expected to be ready for use this year, but VRT NWS reported on 20 November 2026 that the bad weather had stopped the final works: the anti-slip coating could not be laid in damp, cold conditions, pushing the opening back to the spring.
Sources: VRT NWS
Reporting
Opening pushed back
De Vlaamse Waterweg, the Flemish waterways agency, has been unable to finish the new Firtelbrug in Zulte on schedule, and cyclists and pedestrians will not be able to cross it until the spring, VRT NWS reported on 20 November. According to the broadcaster, persistent bad weather prevented the agency from applying an anti-slip coating to the deck of the bridge. Damp air and temperatures that were too low meant the layer could not be laid down, so the crossing remains closed to users for the time being.
Reporting
A link to the cycle highway
The bridge is designed as a link for people travelling on foot or by bike. As VRT NWS describes it, the Firtelbrug runs from the centre of Zulte along the Limnanderdreef to the towpath on the opposite bank of the Leie. From there, cyclists gain direct access to the F371 cycle highway, giving residents of the municipality a straightforward way onto the route without having to look for another crossing over the river.
Reporting
Why the coating matters
The missing coating is not a cosmetic detail. VRT NWS reported that without it the deck carries a real risk of people slipping and falling. The broadcaster added that walking or riding on the bridge before the work is complete could also damage the structure itself. That combination of safety and durability concerns explains why the opening has been postponed rather than allowing provisional use while the weather remains unsuitable for the final layer.
Reporting
Local leaders accept the delay
The delay matters for local mobility because, according to VRT NWS, the bridge was meant to be ready for use before the end of this year, and its main purpose is to connect the town centre with the cycle network on the far side of the Leie. Local politicians have nonetheless backed the decision. Mayor Simon Lagrange and mobility alderman Sophie Delaere, both of Open Zulte, told VRT NWS that it was a shame the bridge could not be used sooner, but that they understood De Vlaamse Waterweg putting quality ahead of speed.
Reporting
What is still unknown
For now, the opening is foreseen only for the spring. The report does not give a precise date, nor does it say how long the coating work itself will take once conditions improve, or whether the postponement has any effect on the cost of the project. Those details are not yet known, and people hoping to reach the towpath and the F371 from the centre of Zulte via the new crossing will have to wait until the anti-slip layer is in place.
Understanding the story
What the main actors are doing
Reported positions, summarised — not direct quotations
De Vlaamse Waterweg
The body carrying out the works on the Firtelbrug. It could not apply the anti-slip layer because of the weather and, according to the local council, chose quality over speed.
Sources: VRT NWS
Simon Lagrange
The mayor of Zulte (Open Zulte) regrets that the bridge cannot be used sooner but says he understands the decision to prioritise quality.
Sources: VRT NWS
Sophie Delaere
Zulte's alderman for mobility (Open Zulte), who shares the mayor's view that the delay is a pity but understandable.
Sources: VRT NWS
Voices & reactions
Simon Lagrange and Sophie Delaere (Open Zulte)
Mayor Simon Lagrange and mobility alderman Sophie Delaere said: "Het is jammer dat we de brug niet sneller kunnen gebruiken, maar we hebben er begrip voor dat De Vlaamse Waterweg kwaliteit boven snelheid verkiest" (it is a pity, but they understand quality is put before speed).
Sources: VRT NWS
Key terms
- Leie
- A river in France and Belgium (Lys in French), a left-bank tributary of the Scheldt that rises in Pas-de-Calais and joins the Scheldt in Ghent, passing Zulte on the way.
Sources: Wikipedia: Lys (river) (Background reference)
People, places and institutions
- FirtelbrugThe new bridge for cyclists and pedestrians whose opening has been delayed until the spring.
- ZulteEast Flanders municipality on the Leie where the new bridge is being built.
- De Vlaamse WaterwegResponsible for the bridge works; unable to apply the anti-slip layer because of the weather.
- F371Cycle highway that cyclists will reach directly via the new bridge and the towpath.
- Simon LagrangeMayor of Zulte (Open Zulte), who reacted to the delay.
- Sophie DelaereZulte's alderman for mobility (Open Zulte), who reacted to the delay.
Sources: VRT NWS · Wikipedia: Zulte (Background reference)
Sources and factual attribution (1)
- Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS Nieuws — VRT NWS
Dated report by VRT NWS used for the facts attributed to it.
Source publication date: . Consulted: .
Supports
Cyclists and pedestrians will only be able to use the new Firtelbrug in Zulte from the spring.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS NieuwsBecause of damp air and temperatures that were too low, De Vlaamse Waterweg could not yet apply the anti-slip coating to the bridge deck.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS NieuwsWithout the anti-slip coating there is a risk of falls, and users could also damage the bridge by walking on it.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS NieuwsThe bridge links the centre of Zulte via the Limnanderdreef to the towpath on the other bank of the Leie, giving cyclists direct access to the F371 cycle highway.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS NieuwsThe bridge was originally expected to be ready for use before the end of this year.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS NieuwsMayor Simon Lagrange and mobility alderman Sophie Delaere, both of Open Zulte, said it was a pity the bridge could not be used sooner but that they understood the choice of quality over speed.
VRT NWS: Firtelbrug in Zulte pas in voorjaar toegankelijk door slecht weer tijdens werkzaamheden | VRT NWS Nieuws
How this article was prepared
Revisions and corrections
No corrections recorded.
- First version · 1 —
First publication.